TSR Renovation Updates #3

We thank God that the renovation works have been advancing well. Moving forward, we will be sharing key progress fortnightly. May we continue to keep this project in prayer!


  • Level 3 toilet’s brickworks, base plaster and waterproofing works have been completed, and the tiling works are about to commence.

Level 3 Toilet in progress
  • Steel Beam has been installed for the Fellowship Deck.

Installation of steel beam in progress
  • Initial payments amounting to approximately $300,000 have already been made or are pending.


Should you have any questions, or concerns, or require more information regarding the renovation, you may reach out to the Church Office @ 8463 2186. Please note that our land line (6284 1987) will be unavailable until further notice.