TSR Renovation Updates #7

We thank God that the renovation works have been advancing well. Moving forward, we will be sharing key progress fortnightly. May we continue to keep this project in prayer!


  • Tiling works for Level 1 toilets are completed 

Level 1 Washroom
  • The new corridor next to the Kitchen (behind the second lift) is up 

Kitchen Corridor
  • 3rd progressive payment of $250,000 coming up

Progress Payment

Payment Amount

Bank Balance

1

$184,787.65

$1,873,103.01

2

$285,386.92 

$1,637,051.69


Should you have any questions, or concerns, or require more information regarding the renovation, you may reach out to the Church Office @ 8463 2186. Please note that our land line (6284 1987) will be unavailable, until further notice.